Recommended Process Flow
1. Foundation Treatment
• Inspect the foundation: Ensure that the concrete or asphalt foundation is flat, solid, clean, without cracks or chipping.
• Clean the surface: Sweep away dust and debris. If necessary, use high-pressure water to rinse.
• Leveling Treatment: Use cement mortar or repair materials to fill in the potholes to ensure a flat surface.
2. Base Layer Installation (Buffer Layer)
• Materials: Black PU glue + SBR particles (common particle size 1-3mm).
• Construction Steps:
1. Mix SBR particles with the special glue in the prescribed ratio (common ratios 1:7 or 1:8).
2. Spread the mixture evenly to the specified thickness (usually 8-10mm).
3. Use a roller to flatten and compact, ensuring a uniform surface.
4. Curing Time: Approximately 24 hours (adjust according to temperature and humidity).
3. Top Layer Installation (EPDM Layer)
• Materials: Colored EPDM particles + PU glue.
• Construction Steps:
1. Mix EPDM particles with the glue in the prescribed ratio (usually 1:6 or 1:7).
2. Spread it evenly on the buffer layer, with a thickness of 3-4mm (up to 5-8mm for kindergartens).
3. Use a trowel or scraper to compact and smooth the surface, ensuring the particles are dense and not loose.
4. Curing Time: Approximately 24 hours.
4. Surface Finishing
• Clean up excess materials at the edges and joints.
• Spray surface protection agent as needed to enhance wear resistance and waterproofing.
• After complete curing, check for any particle detachment or hollow areas and repair them.
What Is The Recommended Process For Laying EPDM Granules? What Supporting Materials Are Required?
Aug 22, 2025